Saturday, June 21- Week 1- Exterior Framing: build and raise the exterior walls
Sunday, June 22- Week 1.5- OSB Installation: install the OSB
Friday, June 27 - Week 2 Interior Framing: build and raise the interior walls
Saturday, July 12- Week 3- Insultation & Siding: insulate the house and install the siding
Sunday, July 13- Week 3.5- Siding Part 2: complete the siding
Saturday, July 19- Week 4- Exterior Paint: paint the exterior walls, trim, and shutters
Saturday, July 26- Week 5- Interior Paint Prep: prepare the walls for painting
Friday, August 1- Week 6- Interior Paint:complete first coat of interior paint
Saturday, August 9- Week 7- Interior Paint & Trim: complete the second coat of interior paint
Saturday, August 16- Week 8- Complete the House: install the hardware and complete the finishing touches
Saturday, August 23- Week 9- Landscaping: lay sod, plant shrubs, and install the mailbox
Ghost Days:
Thursday, June 19- Ghost Day 1- Build Components
Thursday, June 26- Ghost Day 2- Deadwood
Thursday, July 3- Ghost Day 3- Siding Prep
Thursday, July 24- Ghost Day 4- Interior Doors & Trim